Confluence was part of the multi-disciplinary team selected to master plan and document an athletic complex for the new West Central Valley High School in Stuart, Iowa. The scope included a track, football, baseball and softball fields. After a series of meetings and budget exercises, a master plan was developed. After obtaining City approval, Confluence produced construction documents that were bid in three separate packages; Grading and Utilities, Track Surfacing, and General Construction.

The grading and utilities were completed in the fall of 2012. With the track and football stadium completed and ready for play in the fall of 2013. The baseball and softball fields are seeded and will be open for competition in the spring of 2015. The West Central Valley Community School District now has a facility that can host district events and which is a source of community pride.